Timelines vary by deployment combination. Below are typical schedules for each, starting with our recommended configuration.
Lightest footprint. Minimal venue hardware.
| Phase | Duration | Activities |
|---|---|---|
| Pre-Installation | 1–2 weeks | Bandwidth test, confirm ethernet handoff, firewall rules |
| Day 1: Setup | ~3 hours | Mount AP, deploy router, connect to venue ethernet, establish VPN |
| Day 1: Testing & Handoff | ~3 hours | Remote link validation, VR streaming quality check, handoff |
Remote compute, venue handles networking.
| Phase | Duration | Activities |
|---|---|---|
| Pre-Installation | 1–2 weeks | VLAN provisioning, bandwidth test, API credential exchange |
| Day 1: Setup | ~2 hours | Mount AP, connect to venue VLAN, establish VPN to remote compute |
| Day 1: Testing & Handoff | ~3 hours | Remote link validation, VR streaming quality check, handoff |
Heaviest footprint. Full stack on-site.
| Phase | Duration | Activities |
|---|---|---|
| Pre-Installation | 2–4 weeks | Site survey, network planning, confirm checklist items |
| Day 1: Physical Setup | ~4 hours | Rack compute and network gear, mount AP, run cables, connect power |
| Day 1: Network Config | ~2 hours | Router setup, VLAN config, AP configuration, wired clients |
| Day 2: Calibration | ~3 hours | VR streaming validation, latency checks, signal coverage |
| Day 2: Handoff | ~1 hour | Staff walkthrough, documentation, remote access confirmed |
Compute on-site, integrated into venue network.
| Phase | Duration | Activities |
|---|---|---|
| Pre-Installation | 2–4 weeks | VLAN provisioning, API credential exchange, site survey |
| Day 1: Physical Setup | ~3 hours | Install compute, mount AP, connect to venue network |
| Day 1: Config & Test | ~3 hours | AP configuration, VLAN verification, QoS testing |
| Day 2: Calibration & Handoff | ~3 hours | VR validation, documentation, remote access |
Timelines may vary based on venue complexity and readiness of checklist items.
For an event where exhibitors supply the equipment, fault arrivals are heavily front-loaded. Measured over 16 days on a 280-stand expo in October 2026, 197 floor reports in total:
| Period | Reports | Share |
|---|---|---|
| Day 1 | 37 | 19% |
| Day 2 | 37 | 19% |
| Days 3 to 7 | 69 | 35% |
| Days 8 to 16 | 54 | 27% |
That is 37 reports a day while the floor settles, against 6 a day in the second week. Staff the first two days for roughly six times the later rate.
The work also concentrates on few stands. 44 of the 280 stands produced 73 per cent of the reports, and 31 of those 44 were first reported on day one or day two. Build the watch list on the evening of day two from the reports already filed: half of every report that came later came from a stand that was already on it.
Operational guidance for the floor is in exhibitor-floor.md.
All deployment types benefit from the following post-installation practices. The scope depends on the deployment duration.
| Activity | Events | Temporary Exhibitions | Permanent Installations |
|---|---|---|---|
| Remote monitoring and management | During operation | Throughout exhibition run | Continuous |
| Hardware lifecycle and replacement | N/A | As needed | Scheduled replacement cycles |
| Scheduled maintenance windows | N/A | Coordinated with venue | Monthly or quarterly |
| Scaling (adding/removing headsets, bodies, displays) | Pre-planned | As exhibition evolves | On demand |
When a deployment ends: